Dates: November 15, 2004 to November 19, 2004.
Location: ASU New Science Building, Orange St & McCallister Ave, Tempe, AZ
Owner: Arizona Board of Regents/Arizona State University, Tempe, AZ
Contractor: University Mechanical.
Description: SSC provided consulting services to UMEC to design this 64’ tunnel to connect the new building to the chilled water and steam lines on the ASU campus, which is the heating and cooling source for the university’s buildings.
Challenges: SSC had only 6 days to complete this project, working 24 hours a day. Work had to be performed above ground utilizing a unique platform SSC constructed.
Method: Hand Tunneling
Results: SSC’s crews worked 24 hours a day and were able to install 64’ of 48” casing in 4 days. A platform/scaffolding system was designed to elevate the tunneling operation 5 feet off the basement floor of the building to the correct height to tie into the chilled water and steam lines that were existing in the street. Our crews used hand tunneling to create the path for the 48” casing to then be pushed in by the jack and bore machine which was also elevated on the platform. Our tunneling operation prevented the very busy streets of the university from being open cut to tie these lines in. There were many utility conflicts that existed that would have made the open cutting even more difficult. Our innovation allowed for this tie-in to take place without any interruption to the surrounding area.

What Our Clients Say:

  • “Just wanted to say thank you for the safety culture your company has. It’s a breath of fresh air to see other companies embracing being safe. I sat in on your crews’ safety meeting this morning prior to the start of their work on Ray Rd. “

    Scott Nunemaker – Vice President, RCCM

  • “Kuddos to your guys. Not once has any of your foreman’s EVER put up a fuss when I’ve asked them to work a little late. Response is always “whatever you want and we’ll stay as long as you need us to.” I really appreciate all the hard work they do for me. Thank you sir.”

    Travis Barrick – Field Supervisor, Felix Construction

  • “A big thank you to SSC for jumping on this quickly as they did to help the team get this information so quickly. It’s much appreciated and was pretty impressive to see 5 separate potholing crews descend upon Rio Salado the way they did today!”

    Christopher Laute, Resident Engineer, Valley Metro

  • We’ve used SSC for a number of years and I’ve been very pleased. Thanks and keep up the great work.

    Dave Klann, Staff Engineer, Mactec

  • SSC did a great job. Their assistance during pre-construction was greatly appreciated and differentiated them from the competition. Keep doing what you do best!

    Jim Drago, Sundt Construction

  • I called with short notice to some work and SSC responded immediately. In this market, dollars seem to control everything and quality of people and work seem to have diminished. The professionalism and hard work of your crew takes me back to when people knew what they were doing and cared. Intelligent guys that work […]

    Lonnie Ferguson, Project Manager, Construction 70

  • As a civil engineering consultant, I usually recommend your services but rarely use them with the exception being vacuum excavating. I have attended your seminars in the past and find them very helpful. I recommend continuing the education to make designers better. If we understand and know how to specify your service, we are more […]

    Bill Gasque, Sr. Civil Engineer, Dowl HKM

  • SSC handled the project perfectly even went above to schedule directly with the gas company, made my job easier.

    Tony Smith, Owner, Western Underground

  • You and your staff are always responsive to our needs and make sure you clearly understand the scope of the work in advance, so there are no surprises. I really appreciate that attitude.

    Michael Rhodes, Civil Engineer, Gila River Indian Community

  • Overall a good company. Very professional in approach and execution of work. Courtesy and respect shown by all personnel, a welcome rarity in the business. Keep doing what you’re doing, and thank you.

    M. Gartner, Project Manager, Sybrant Construction

  • We have been using your company’s services for about 3 years now. I have never heard a negative comment. Bringing Curtis on board is a definite plus as far as I am concerned. He keeps me informed about the work that I have done and he is very through and dependable.

    David Cross, Utility Coordinator, MCDOT

  • Your field crew did a great job!

    Nick Nikrant, Project Manager, Builders Guild

  • Crew was courteous & helpful.

    Jayde Bullard, Project Manager, Caljet of America, LLC.

  • This is the second time working with this foreman. Will request him again. Easy to work with.

    David Willett, Aero Automatic Sprinkler Co.

  • Superb foreman…Exceptional!

    Curtis Briggs, Shea Homes

  • Great work! SSC was timely, responsive and professional. I would use them again.

    Stewart Vaghti, Project Engineer, Gannett Fleming, Inc.

  • I have always had good and quick service from SSC.

    Sally Raymer, Sundt Construction

  • Arvid was very accommodating in getting crew onsite within 2 hours of my call.

    Dennis Sime, Project Superintendent, Hunter Contracting

  • First I want to express once again how impressed I am with you and your support group. You are all “top notch.” Yes the job went well and I appreciate your help. It really made a huge difference on such a critical facility. I still can’t believe (even though I saw it with my own […]

    David McKinley, VFC-Arizona

  • Great service on short notice. Thanks!

    Richard Komzelman, Carson Construction

  • The entire SSC crew was extremely professional and flexible. All of your company’s efforts are greatly appreciated and you will be our boring subcontractor on any future projects.

    Ben Myers, Project Manager, GRG Construction

  • Your team made this challenging casing push a success.

    Michael Fossett, Project Manager, SDB Inc.

  • Extensive knowledge of the local soil conditions coupled with their proven skills has insured that every job is completed within our schedule and budget. We’ve worked with SSC for many years and always found them to more than equal our high required standards and able to complete any task.

    Brian Chavez, Chief Estimator/Project Manager, Tyers Contracting

  • I would like to thank you for your prompt response to our urgent need for your services. The men you sent did a fantastic and quick bore. We do so appreciate your company for that. Thanks!

    Patricia Riggs, Town of Gila Bend

  • Our job was especially challenging. The SSC team worked six days, around the clock and the testimony to the success of their efforts is that the general public never knew they were here. An additional thanks to SSC for their professional courtesy. In our industry, it is something I do not encounter often enough.

    Chris McCoy, Superintendent, Gilbane Building Company

  • Your project manpower’s knowledge, attitude, safety and work ethic are outstanding!

    Mike Levi, Estimator/Project Manager, Holloman Corporation